Objective: first cross-system test of beam based systems to exercise:
using high level control room software.
Would aim to set-up using stand alone applications (LSA for the most part) and then drive sub-set of machine through 450 GeV operational phases: pre-injection plateau, ramp to injection, injection plateau pre-beam, injection using machine sequencer. Include as much of TI8 as possible.
When: Friday 14th & Monday 17th December 2007
Friday: individual system tests outline
Monday: As a collective from sequencer.
LSA | Requirements | Aux | S/W | Hardware | ||
Timing | Define events. Construct timing tables. Forewarning events must be generated from a table that you load that is triggered from HIX.FW-CT, this is just a normal timing table loaded by OP as usual. A system task triggers production of HIX.FW-CT when the SPS extraction forewarning arrives. |
V0.1 | Need application up and running and debugged. Configure, load and send tables. Change & Monitor contents of telegrams (TGM video tool - crank it up for the LHC). Check subscription. Distinction between fast extraction event for CNSG and LHC in the SPS? LHC as master - set. |
Delphine | Julian, Stephane, Ioan | |
Power Converters | As many as Steve Page can give us (expect around 200) Act HW Group 'DRY RUN DEC 07' |
V0.1 | injection, ramp&squeeze - test what ever we can get hold of - in voltage simulation. Cold magnets a possibility if available. Would be looking for several hundred converters in total. | logging, monitoring | Mike | Stephen Page |
RF | Monitor? | Not this time. No pre-pulses. (Although could imagine monitoring ongoing commissioning.) | Delphine | Andy | ||
Injection Kickers | Kicker parameter space (include kick strength), Kicker control application Acquire waveform - OASIS |
to do | plus make rule, discrete trim (check - should go trim) | logging | Lasse/GHH | Etienne |
TDI | Test settings and monitoring. By the way, it will be difficult to move the *real* TDI's for the injection test |
Stefano's application, settings, trim | logging | Stefano | Kadi | |
Beam Dump | Monitor, XPOC | XPOC - more space, more space.... | Jerome | Bren | ||
BPMs | Concentration - capture & FIFO | V0.1 |
fixed display - first turn FIFO, first turn capture (Jakob) naming convention? layout versus MAD |
sdds logging?? |
Marek M. | Lars |
BLMs | Concentration | V0.1 | TI8 BLM - running display (fabio?) |
logging | Marek M. | Lars |
Screens | Control, acqusition | to do | Display, logging, VIDEO | Fabio, Guy | Lars | |
BCT | Acquistion | V1 | Display, logging | Markus | Lars | |
Fast BCT | We can basically acquire selected bunches over consecutive turns. | prepare a first version of an application concentrating on the DabCapture mode and probably also provide a fixed display for the standard Acquisition mode (all bunch intensities averaged over 227 (?) turns) | Markus | Lars | ||
Lumi Monitors | Acquire & display | Markus | ||||
Wire scanners and sync light monitors | Start applications and displays | Elliot | ||||
BIC | ?Not sure what's going to be there. | Not there - not installed |
LSA | Requirements | S/W | Hardware | ||
Optics | Twiss/Strengths/Generation | V0.2 | Define supercycle for test. Injection, ramp & squeeze Issues: actual optics name, reading settings (12 seconds), generate warm correctors, trim - DBP name, trim - makerule problem |
Marek S | |
Knobs/MAD | Injection bumps, injection point steering, septa | TI8/LHC cross over MSI, kicker knobs from YASP |
Verena, Jorg | ||
Database | Parameter space etc. etc. etc. | V0.1 | ramp & squeeze, power converters, kickers, instrumentation, | Chris, Delphine, Mike | |
FIDEL | Harmonics, decay, snapback | V0.1 | Injection plateau | Marek S. | |
Mode | Definition, distribution | Publish... | Mike, Reyes, Greg | ||
Timing | Monitor contents of telegrams | Delphine | Julian, Stephane, Ioan | ||
DIP | Experiment communication | Define signals to push and pull. - how do we push? | Markus | ||
RBAC | Aim for a full vertical slice | Suzanne | Steve Page |
LSA | Requirements | Aux | S/W | Hardware | ||
YASP |
Acquisition and correction The acquisition of the BeamThreading stuff is working in YASP (for the first turn) for a selected crate. In principle I could go for more crates, but I will wait now for the concentrator. |
YASP - Jorg
|
Marek M., Jorg | |||
Sequencer | Multi system Drive | V2.0 | Sequence definition | Reyes, Mike | ||
Fixed Displays |
|
Reyes/Vito/Roman
DR | LSA | Other Agent | S/W | H/W | ||
X | Pre-cycle power converters | |||||
X | Set to pre-injection plateau level | |||||
X | ramp to injection level | |||||
Check/Monitor | Check & monitor power converter settings | SSIS | ? | Stephen | ||
Settings/Drive | Set TDI settings “parked”, "coarse", "protect" | Settings space? | ||||
Settings/Drive | X | Set collimators “parked” | ||||
Drive | X | Set kicker settings | OK | Etienne | ||
Drive | X | Set Injection kickers ON | OK | Etienne | ||
FiDeL/Trim | X | Start auto harmonic decay correction | OK | Marek S | ||
Check/Monitor | Check and monitor transfer lines | SSIS | ? | |||
Check | X | Beam dumps "ready" | ||||
Settings | X | Set BPM gains to pilot, set capture bunch and turns | What sort of settings are these? | Lars | ||
Check | Check Beam interlock system | Not ready | BIS | |||
Drive | ? | Change injection master to LHC | Check timing API | CBCM | Stephane | Julian |
Settings/Drive/Check | RF 400 MHz ON and set | |||||
Settings/Drive/Check | Set & check RF frequency | |||||
Settings/Drive | Load LFB, TFB settings | |||||
Drive | Set RF frequency program to injection level | |||||
Drive | Set the gain of the phase loop amplifier to filling value | |||||
Drive | Set the gain and time constant of the synchronization loop amplifier to the filling value | |||||
Drive | Close the phase loop around the VCO | |||||
Drive | Switch the RF DRIVE ON | |||||
Drive | Switch the phase loop to the cavity sum signal | |||||
Drive | Reset the revolution frequency generator | |||||
Check synchronization. |
DR | LSA | Other Agent | ||
Drive | X | Load and/or check injection timing table | CBCM | |
Drive | X | Make request to CBCM with ring, bucket number, PS user (intensity) and number of PS batches | ||
Timing | X | Injection into LHC - injection kickers, BI receive pre-pulses. BST sends out acquisition event for BPMs, BLMs as required. | Acquire [BCT, BPMs, BLMs, SRM] | |
On event | LFB,TFB,RF: Batch dependent settings triggered by timing events. |
|||
After kick | X | Acquire kick waveform | OASIS |
Followed by post-injection checks - did acquisition, concentration, publish, timestamping etc. work? Repeat as necessary.
DR | |||
Manual | Check first turn, energy offset, beam loss, intensity, emittance, RF response, longitudinal emittance | ||
Automatic | X | Check BLMs, trajectory in transfer line | |
Manual | X | Measure tune, orbit, chromaticity | |
Sequencer | Configure and start global orbit feedback | ||
Automatic | Monitor lifetime, beam losses | ||
Automatic | Monitor harmonic correction | ||
Sequencer | TDI,TCDQ to coarse | ||
Sequencer | X | Collimators to coarse | |
Sequencer | X | Change mode |
DR | |||
Incorporate trims | |||