LHC 2012 - latest news

Week 35: Machine coordinators: Gianluigi Arduini, Jan Uythoven

Plan for the week: Luminosity production

Date

Summary

Link to report from morning meeting

Mon 3 Sep
  • 00:08 Injecting
  • 00:58 OFC crashed at the beginning of the squeeze. SIS dump. Expert called. Core dump saved
  • 02:00 Filling and verification of the behaviour of the orbit and tune feedback.
  • 03:25 Stable beams #3023. Initial luminosities up to 7.1x1033 cm-2s-1
  • 03:28 Lost cryogenics in sector 78. QRL vacuum gauge spurious reading and triggering closure of cryo valves on DFB
  • 07:10 Access in point 7 for replacing vacuum PLC in IP7
08:30 meeting
Sun 2 Sep
  • 01:23 STABLE BEAMS #3020. Initial luminosity 6.9x1033 cm-2s-1
  • 06:17 RQTL7.L7B2 trip (QPS – requiring QPS reset – SEU?). 87 pb-1 in ~5 h
  • 07:13 Start filling
  • 09:08 STABLE BEAMS #3021. Initial luminosity 6.6x1033 cm-2s-1
  • Beam dump initially planned for ~20:00 delayed to 22:00 to allow MKI B1 kicker temperature reduction
  • 22:05 OP dump (167 pb-1 in ~13 h). Injection delayed due to MKI2 temperature
09:00 meeting
Sat 1 Sep
  • 08:03 Operator dump, integrated lumi’s 173 pb-1
  • 08:40 Trip of RQX.R1 during ramp down, same as yesterday afternoon during ramp up
  • 09:00-10:00 Test cycle for the triplet R1. OK from PO piquet to continue operation
  • 11:35 STABLE BEAMS #3019. Initial luminosity  ~6.64x1033 cm-2s-1
  • 17:10 Trip of RQT13.R7B1 (QPS - likely SEU). ~92 pb-1 in 5.6 h
  • In parallel TCTVA.4R5.B2 problem.
  • 21:13 After several attempts to reset the QPS controller for RQT13.R7B1 remotely access for QPS board replacement
  • 22:17 access finished. Precycling
9:00 meeting
Fri  31 Aug
  • 00:03 Stable beams #3016. Initial luminosity ~6.7x10^33 cm-2s-1.
  • 08:59 Electrical network glitch - Beam dump - ~125 pb-1 in 9 hours.
  • 11:36 At the end of the pre-cycle another electrical problem appeared in point 8
  • Problems with the beams from the BOOSTER and a vacuum spike in the SPS extraction kicker (LSS4)
  • 14:33 Injection physics beams ¨Large emittances from the injector chain, up to 2.6um for B2V.
  • 15:33 Lost beam at the very end of the ramp (3.9 TeV), Trip of IT.R1. 
  • 18:55 Stable beam fill #3018, initial lumi  6.6e33 cm-2s-1 
8:30 meeting
Thu 30 Aug
  • 01:00 Cryo Start IP2 back
  • 01:29 LHCb dipole tripped due to electrical perturbation ¨OK for restart…
  • 02:46 POPS back in the PS
  • 08:30 Access for vacuum in IP4 to get vacuum equipment out.
  • 11:00 Vacuum intervention on BSRT finished
  • 12:14 Problems to restart RF module M2B1. Piquet called. Access required.
  • 13:40 Start injection fill 3014 - pilot ramp for LHCb polarity check (2x6 on 2x6 bunches)
  • 16:30 Setting-up completed- OP dump
  • 17:25 Filling #3015. Problem with TI2 power converter
  • 18:49 TI2 Ok. Filling
  • 20:39 Stable beams #3015. Initial luminosity ~7x10^33 cm-2s-1.
  • 20:39 Trip of RQTL7.R7B2. Beam dump
8:30 meeting
Wed 29 Aug
  • 04:00-07:00 Octupole polarity verification on MOD.A23.B1 with pilot bunch. Polarity OK.
  • 07:30 start of access for intervention on BSRT
  • 11:00 BSRT mirror and arm removed. Pumping down.
  • 13:21 Compensator in Point 2 down
  • 21:32 A first attempt to connect the SR2 TCR compensator caused the trip of the filter and consequently of the IP2 cold compressor. ¨Also problems RB12 and RB23
8:30 meeting
Tue 28 Aug
  • 02:09 Stable beams fill #3011, initial lumi 7.4e33 cm-2s-1
  • 14:09 End of fill #3011. OP dump. ~175 pb-1 in 12 hours.
  • Afternoon: issue with BSRT mirror beam 2. Investigations by BI
  • 19:00-21:00 BI access for BSRT issue
  • 23:00-02:00 Access for vacuum team for Neon Injection in preparation of intervention on BSRT.
8:30 meeting
Mon 27 Aug
  • 00:50 Stable beams fill 3007,  initial Luminosity ~6.8E33 cm-2s-1
  • 03:40 Beam dumped by OP due to cryo problem in Pt4, integrated L ~ 56 pb-1.
  • Cryo compressor off in Pt4.
  • 08:00 Start accesses
  • 16:00  Cryo conditions back
  • 17:00 Cycling the magnets
  • 18:30 Injecting batches of 6 for steering TI2, seems ok.
  • 19:18 Inject for physics
  • 19:30 No beam anymore from SPS – dump half way filling Extraction septum problem – call specialist
  • 21:47 Injecting for physics again
  • 23:00 Stable beams fill #3009, initial lumi 7.3e33 cm-2s-1
  • 23:27 Beam dump – UFO 5L4
8:30 meeting