LHC 2012 - latest news

Week 11 Checkout coordinators: R. Giachino, M. Albert --> Tuesday

Machine coordinators : G. Arduini, J. Wenninger

Beam Commissioning Planning

 

Date

Summary

Link to report from morning meeting

Monday 19th Mar

  • 02:00 Ramp and squeeze attempt. Lost due to bad reading of a temperature sensor in cell 23.R7.
  • 06:30 Another ramp and squeeze: lost on third integer in the squeeze beyond 2 m.
  • 08:30 Start another ramp

8:30 meeting

Sunday 18th Mar

  • 02:00: ramp and squeeze for optics measurement
  • 04:11 Dump due to spurious BLM trigger
  • Optics measurements ongoing during the squeeze. No beam form SPS (RF transmitter problem).
  • 10:00 Beam available from SPS.
  • 11:15: Beta*=0.6 m in IP1/5 with beam 1 and beam 2
  • 13:00 Optics measurements completed.
  • 15:00: Spurious dump from FMCM_RD34.LR7.
  • 17:00 ALICE and LHCb spectrometers/solenoids ON, all with polarity +.
  • 17:30: Spurious dump from FMCM_RD34.LR7.
  • 18:15: All separation and crossing bump angles ON at injection.
  • 18:30: Ramp attempt with probes, separation and crossing ON.
  • Problems with the tunes and tune FB at the first squeeze point. Lost beam2.
  • 21:00: Another attempt of R&S with dynamic FB references. Dump at 262 s in squeeze. OK for OFB.
  • 23:00 Decay measurements after ramp-down

9:00 meeting

Saturday 17th Mar

  • Night: First global aperture measurements and validation of controlled transverse blow-up for loss maps and aperture measurements
  • Ramped at 4 TeV. Again glitch in safe beam flag after the end of the ramp. Beam 2 dumped. 
  • Problem with extraction septum MSE.418 in SPS - no beam2 injection.
  • 13:00 Ramp and squeeze test with B1.
  • 16:35 Beta*=0.6 m in IP1/5 with beam 1.
  • 18:00  Beam 2 not yet available from SPS go for optics measurements at 60 cm on beam 1 only.
  • 19:30 Optics measurements at 60 cm completed.
  • 20:00 No beam 2 form SPS yet. ==> Setting-up of damper with nominal bunches. Transverse blow-up setting-up for beam 2.
  • 20:30 Beam 2 available

9:00 meeting

Friday 16th Mar

  • FGC software update (RT trims). Access in PT1 for dump resistor in S81 and corrector.
  • 10:30 Closing machine.
  • 11:00 RQX.L2 tripped: problem with sub-converter - access required
  • 12:45 machine closed - precycling
  • No beam form PS: Main Power Supply problem (POPS)
  • 15:30 Ready to inject
  • 15:30 - 21:30 Setting-up of tune feedback and orbit feedback, setting-up of the controllled transverse blow-up
  • 21:50: vacuum gauge outgassing ==> beam dump
  • 22:30 Start ramp
  • 22:43 Flat-top. 4 TeV with both beams
  • Beam 2 dumped by glitch in the SAFE beam flag (noisy BPM.LSS6)

8:30 meeting

Thursday 15th Mar

  • Morning : Optics measurements and corrections at 450 GeV. Beta-beating corrected to 5%.. In parallel Q and Q' measurement setup.
  • Afternoon: transfer line steering with probe, BPM non-linearity scan in IR5, injection of nominal bunch.
  • Evening: reference orbit with nominal bunch, BPM quality check, SIS orbit and COD interlock tests at injection.
  • 20:00 Test of collimator setup with fast BLM acquisition.
  • Night: BI shift

8:30 meeting

Wednesday 14th Mar

  • Morning: machine closed, cycle tests, MKI tests
  • 15:30 SPS ready. LHC completing MKI tests
  • 17:30 Ready for injection but problem with SPS extraction for beam 1 and  SMP distrribution.
  • In parallel problem with the extraction of B1 (kicker MKE6), traced to a problem with an electronic card - replaced at 20:15, but new card has a problem and kick delay is not correct.
  • 21:30 MKE6 delay problem solved - card configuration.
  • 22:30 SMP problem fixed - repeater added on the BA4 side to increase signal in CCR/BA3.
  • 23:00 Injecting into LHC.
  • 23:40 B1 circulating.
  • 00:30 B2 circulating.
  • 01:00 Closed orbit corrected on both beams. Correcting Q and Q'. RF capture.
  • Overnight RF capture tuning.
  • 04:00 Start optics measurements.

8:30 meeting- checkout

08:30 meeting - beam commissioning

Tuesday 13th Mar

  • Morning : access.
  • Afternoon : machine closed, LBDS and MKI tests,

8:30 meeting

Monday 12th Mar

  • Access.
  • Experiments handshake and SMP tests in the afternoon.
  • Machine sequence test overnight.

8:30 meeting

Beam commissioning