LHC 2012 - latest news
Week 11 Checkout coordinators: R. Giachino, M. Albert --> Tuesday
Machine coordinators : G. Arduini, J. Wenninger
Beam Commissioning 
Planning
 
 
 
  | Date | Summary | Link to report from morning meeting | 
 
  | Monday 19th Mar | 
   02:00 Ramp and 
	squeeze attempt. Lost due to bad reading of a temperature sensor in cell 
	23.R7.06:30 Another ramp 
	and squeeze: lost on third integer in the squeeze beyond 2 m.08:30 Start another 
	ramp | 
	8:30 meeting | 
 
  | Sunday 18th Mar | 
   02:00: ramp and squeeze 
	for optics measurement04:11 Dump due to 
	spurious BLM triggerOptics measurements 
	ongoing during the squeeze. No beam form SPS (RF transmitter problem).10:00 Beam available 
	from SPS.
	11:15: Beta*=0.6 m in 
	IP1/5 with beam 1 and beam 213:00 Optics 
	measurements completed.15:00: Spurious dump 
	from FMCM_RD34.LR7.17:00 ALICE and LHCb 
	spectrometers/solenoids ON, all with polarity +.17:30: Spurious dump 
	from FMCM_RD34.LR7.18:15: All separation 
	and crossing bump angles ON at injection.18:30: Ramp attempt 
	with probes, separation and crossing ON.Problems with the 
	tunes and tune FB at the first squeeze point. Lost beam2.21:00: Another 
	attempt of R&S with dynamic FB references. Dump at 262 s in squeeze. OK for 
	OFB.23:00 Decay 
	measurements after ramp-down | 
	9:00 meeting | 
	
  | Saturday 17th Mar | 
   Night: First global 
	aperture measurements and validation of controlled transverse blow-up for 
	loss maps and aperture measurementsRamped at 4 TeV. 
	Again glitch in safe beam flag after the end of the ramp. Beam 2 dumped. Problem with 
	extraction septum MSE.418 in SPS - no beam2 injection.13:00 Ramp and 
	squeeze test with B1.16:35 
	Beta*=0.6 m in IP1/5 with beam 1.18:00  Beam 
	2 not yet available from SPS go for optics measurements at 60 cm on beam 1 
	only.19:30 Optics 
	measurements at 60 cm completed.20:00 No beam 2 form 
	SPS yet. ==> Setting-up of damper with nominal bunches. Transverse blow-up 
	setting-up for beam 2.20:30 Beam 2 
	available | 
	9:00 meeting | 
	
  | Friday 16th Mar | 
	FGC software update 
	(RT trims). Access in PT1 for dump resistor in S81 and corrector.10:30 Closing 
	machine.11:00 RQX.L2 tripped: 
	problem with sub-converter - access required12:45 machine closed 
	- precyclingNo beam form PS: Main 
	Power Supply problem (POPS)15:30 Ready to inject15:30 - 21:30 
	Setting-up of tune feedback and orbit feedback, setting-up of the 
	controllled transverse blow-up21:50: vacuum gauge 
	outgassing ==> beam dump22:30 Start 
	ramp22:43 
	Flat-top. 4 TeV with both beamsBeam 2 dumped by 
	glitch in the SAFE beam flag (noisy BPM.LSS6) | 
	8:30 meeting | 
 
  | Thursday 15th Mar | 
   Morning : Optics 
	measurements and corrections at 450 GeV. Beta-beating corrected to 5%.. In 
	parallel Q and Q' measurement setup.Afternoon: transfer 
	line steering with probe, BPM non-linearity scan in IR5, injection of 
	nominal bunch.Evening: reference 
	orbit with nominal bunch, BPM quality check, SIS orbit and COD interlock 
	tests at injection.20:00 Test of 
	collimator setup with fast BLM acquisition.Night: BI shift | 
	8:30 meeting | 
 
  | Wednesday 14th Mar | 
   Morning: machine 
	closed, cycle tests, MKI tests15:30 SPS ready. LHC 
	completing MKI tests17:30 Ready for 
	injection but problem with SPS extraction for beam 1 and  SMP 
	distrribution.In parallel problem 
	with the extraction of B1 (kicker MKE6), traced to a problem with an 
	electronic card - replaced at 20:15, but new card has a problem and kick 
	delay is not correct.21:30 MKE6 delay 
	problem solved - card configuration.22:30 SMP problem 
	fixed - repeater added on the BA4 side to increase signal in CCR/BA3.23:00 Injecting into 
	LHC.23:40 B1 circulating.00:30 B2 circulating.01:00 Closed orbit 
	corrected on both beams. Correcting Q and Q'. RF capture.Overnight RF capture 
	tuning.04:00 Start optics 
	measurements. | 
	8:30 meeting- 
	checkout 
	08:30 
	meeting - beam commissioning | 
 
  | Tuesday 13th Mar | 
   Morning : access.Afternoon : machine 
	closed, LBDS and MKI tests, | 
	8:30 meeting | 
 
  | Monday 12th Mar | 
   Access.Experiments handshake 
	and SMP tests in the afternoon.Machine sequence test 
	overnight. | 
	8:30 meeting 
	Beam commissioning |