Day |
Short
summary/plan |
Link to reports from 8:30 and 17:00
meetings |
Saturday
26th June |
- Morning: Test ramp with new sequence for squeeze and
collapsing of seperator bumps.
- Afternoon: Fill for Physics with 'Stable Beam' conditions
|
Report
from 08:30 meeting
Observations
during beam loss at Physics fill from Friday
|
Friday
25th June |
- LBDS studies and verification finished
- TOTEM Roman pot adjustment at 450 GeV
|
Report
from 08:30 meeting |
Thursday
24th June |
- LBDS studies and verification
- SPS compensator and TI* technical problems
- Physics fill with 3 nominal bunches per beam
|
Report
from 08:30 meeting |
Wednesday
23rd June |
- 10:00 : Access for RB78 and BIC/RF IR4.
- 12:00 : Machine closed.
- Cryo recovery (Pt4 and Pt2)
- Technical stop in the SPS
|
Report
from 08:30 meeting |
Tuesday
22nd June |
- 04:00 : Asynch. dump test on B1+B2 with 2 mm offset.
- 07:00 : Injection 2.5E10 for asynch. dump test.
- 10:30 : Beam dumped - RB78 fault just before asynch dump
test.
- 11:00 Cryo problem in Pt4.
- 18:00 Cold compressor problem Pt4 during cryo recovery.
|
Report
from 08:30 meeting |
Monday
21st June |
- Midnight - 3:00 : Controlled beam scraping before
asynchronous beam dump. Failed.
- 3:00 : Combo ramp down
- 5:00 : 450 GeV LBDS setting-up and qualification.
- 17:00 : Injection for asynch dump test. Inject 2bx2b
(single_2b_1_1_1).
- 18:00 : B2 lost in the ramp, RF cavity quench.
- 21:30 : Asynch. dump test on B1 with 2 mm offset.
- 23:30 : Injection 2.5E10 for asynch. dump test.
|
Report
from 08:30 meeting
Serge Claudet presentation |