Aim: initial commissioning with the goal to bring moderate intensities into collision for the first time, including the the commissioning the LHC cycle with low intensity beam to high energy, and the move to two-beam operation. See Chamonix XIV presentation for outline.
We aim to minimize the risk of quenches (reduced beam current and possibly reduced energy); decouple the commissioning of the various systems; minimize the pile-up in the experiments; and maximize the integrated luminosity.
Assume we slice commissioning procedures to the minimum required to get 2 pilot++ beams to 3.5 TeV and collide them unsqueezed. From scratch (no sector test, no 450 GeV run):
Phase |
Schedule/Progress Notes |
Ring factor |
Total Time [days] both rings |
Comments | |
A1 |
2 |
- |
Time includes injection tests - take as given in 2009 | ||
A2 |
2 |
4 |
|||
A3 |
2 |
4 |
|||
A4 |
2 |
2 |
Priority 1 measurements only | ||
A6 |
1 |
1 |
Low intensity | ||
A7 |
1 |
2 |
Performance Bring CMS solenoid on before - measure and correct coupling | ||
A8 |
2 |
6 |
Single and then two beams | ||
A9 |
2 |
1 |
Single beam initially, performed following successful ramp | ||
A12 |
1 |
||||
A10 |
1 |
1 |
|||
Physics un-squeezed |
1 |
- |
|||
TOTAL to first collisions |
22 |
||||
A11 |
2 |
6 |
|||
A5 |
2 |
6 |
|||
Set-up physics - partially squeezed. |
1 |
2 |
|||
We are assuming around 30 days of beam time to get first collisions. This will be followed by a period of pilot physics interleaved with further machine development.
TEVATRON
By way of comparison, the Tevatron when it started-up initially in fixed target mode way back when:
RHIC:
First Physics - 2000 following "engineering run" in 1999.
• First beam April 3rd
• First successful ramp: June 1st
• First collisions June 12th
i.e. 2 and a half months for first collisions