Stage A: Initial commissioning to pilot physics

Aim: initial commissioning with the goal to bring moderate intensities into collision for the first time, including the the commissioning the LHC cycle with low intensity beam to high energy, and the move to two-beam operation. See Chamonix XIV presentation for outline.

We aim to minimize the risk of quenches (reduced beam current and possibly reduced energy); decouple the commissioning of the various systems; minimize the pile-up in the experiments; and maximize the integrated luminosity.

Stage A: How Long?

Assume we slice commissioning procedures to the minimum required to get 2 pilot++ beams to 3.5 TeV and collide them unsqueezed. From scratch (no sector test, no 450 GeV run):

Phase
Schedule/Progress
Notes
Ring
factor
Total Time [days]
both rings
Comments
A1
Injection and first turn
First turn
2
-
Time includes injection tests - take as given in 2009
A2
Circulating beam
Circ. beam
2
4
 
A3
450 GeV initial commissioning
 
2
4
 
A4
450 GeV optics measurements
 
2
2
Priority 1 measurements only
A6
450 GeV - two beams
 
1
1
Low intensity
A7
Collisions at 450 GeV
 
1
2
 Performance    Bring CMS solenoid on before - measure and correct coupling
A8
Snapback and ramp
 
2
6
Single and then two beams
A9
3.5 TeV flat top checks
 
2
1
Single beam initially, performed following successful ramp
A12
Commission experimental magnets
 
 
1
 
A10
Setup for collisions - 3.5 TeV
 
1
1
 
Physics un-squeezed
 
1
-
 
TOTAL to first collisions
 
22
 
A11
Commission squeeze
2
6
 
A5
Increase intensity
2
6
 
Set-up physics - partially squeezed.
1
2
 
Pilot physics run
 

We are assuming around 30 days of beam time to get first collisions.  This will be followed by a period of pilot physics interleaved with further machine development.

TEVATRON

By way of comparison, the Tevatron when it started-up initially in fixed target mode way back when:

RHIC:

First Physics - 2000 following "engineering run" in 1999.
• First beam April 3rd
• First successful ramp: June 1st
• First collisions June 12th
i.e. 2 and a half months for first collisions