beam 1 | beam 2 | Fast track | Total Time both rings |
|
Commission TI8 & TI2 end transfer line, injection region, beam to TDI | 12 | 12 | 24 | 24 |
Commission trajectory acquisition and correction, thread beam - first
turn, energy matching |
24 | 24 | 48 | 48 |
Commission Beam Loss Monitor system - phase 1 |
parasitic | 12 |
||
Optics measurements, kicks, trajectory, polarity checks |
12 | 12 | 24 | 24 |
Aperture checks |
skip | 16 |
||
Momentum aperture | if problem | 6 |
||
Setting up of injection machine protection | skip | 12 |
||
Completed in 2008 injection tests | 4 days | 142 hours 6 days |
beam 1 | beam 2 | fast track | Total Time |
|
Adjust chromaticity, close trajectory, obtain closed orbit | 12 | 12 | 24 | 24 |
Integer tunes, fractional tunes, phase advance per turn |
8 | 8 | 16 | 16 |
Energy matching and correction, B-sps, f-lhc, B-lhc - both
rings, RF capture |
16 | 16 | 32 | 32 |
Completed for beam 1 in September 2008 - to be revisited. |
72 hours 3 days |
beam 1 | beam 2 | fast track | Total Time both rings |
|
RF: Beam control loops (Phase, Synchro, Radial). Tuner loop, RF Feedback loop. Synchronisation | 24 | 24 | ||
Test control and correction (orbit, BPM & corrector polarity, cabling, control system, software, procedures, …). | 12 | 12 | 24 | 24 |
Commission transverse diagnostics - Tune measurement [FFT]. Adjust tunes, orbit, chromaticity, coupling. |
12 | 12 | 24 | 24
|
Linear optics checks: check trajectory versus kick, phase advance, | 12 | 12 | 24 | 24
|
Commission beam loss monitors - acquisition, display etc. no connection
to BIC for the moment - phase 2 |
parasitic | 12 |
||
Commission beam dump - phase 1 | 24 | 24 |
||
Commission beam interlock system with beam - phase 1. BIC to dump
with beam. Basic tests with beam. |
assume ok from checkout | 8 |
||
Commission BCTs: lifetime measurement | parasitic | - |
||
Cycle machine - reinject | ||||
4 days | 5 days |
beam 1 | beam 2 | Total Time both rings |
|||
BT | Matching between TI8/Ti2 and ring. Pilots. | skip | 8 |
||
AP/OP | Measure beta beating. Determination of Twiss functions. Need to establish standard procedure to identify and correct all local sources of phase advance errors. | 16 | 16 |
||
AP/OP | Revisit mechanical aperture checks. Bumps - check the aperture in the cold machine is free and has the expected size | 16 | 16 |
||
AP/OP | Field quality checks. Check design fields, field harmonics, fields due to offsets between beam and magnet | skip unless obvious problem | 16 |
||
AP/OP | Momentum aperture | 8 | 8 |
||
AP/OP | IR bumps, check aperture in IRs | skip | 6 |
||
OP/AP/MA | Transfer functions (separation dipoles etc.) | 8 | 8 |
||
OP | Reproducibility after cycling machine. Effect of magnetic cycle, reproducibility, field model | let this come naturally | 16 |
||
OP/AP/BDI | Quench levels and BLM response | skip | 24 |
||
2 days | 118 hours |
beam 1 | beam 2 | Total Time both rings |
|||
RF | Loop adjustment | 8 | 8 |
||
RF | Transverse damper | skip | 16 |
||
RF | Longitudinal feedback | 4 | 4 | 8 | 8 |
BI | Transverse profile monitors | parasitic | 8 |
||
BI | Commission beam loss monitors - phase 2, calibration, thresholds. Commission the BLM's around the collimators. Link to BIC | 8 | 8 | mimimum 16 |
16 |
BI | Tune - PLL | parasitic | 8 |
||
OP | Closed orbit feedback | skip | 16 |
||
COL | Adjustment of collimators, orbit stabilization, test positioning procedures, beam loss monitors. Positioning of jaws with respect to closed orbit. Establish a coarse set of collimator settings. Looking a minimum set of primaries in first instance. This for basic protection up the ramp. | mimimum protection scheme 16 | 36 |
||
BT | TDI. Position, angle, interlocks | 4 | 4 | 8 | 8 |
BT | TCDQ orbit at 6, position, angle, interlocks | 8 | 8 | 16 | 16 |
MPS | FMCM | comm without beam | 4 |
||
MPS | Test Safe LHC Parameters: Safe Beam Flag, Beam Presence Flag, Safe LHC mode, Safe Energy, Safe Squeezing Factor | 8 | 8 |
||
3 days | 152 hours |
fast track | Total Time both rings |
||
OP | SPS - switch rings - TI8/TI2 in parallel | should have been done before | - |
OP/BT | Commission separation bumps. Closure of bumps. Check aperture. Check injection region. | 16 | 16 |
OP/AP | Effect of bumps - dispersion, non-closure | skip or get above | 8 |
BI | Beam parameters: Q split, Q' split, coupling, Beam instrumentation: BLMs, BPMs cross talk etc. |
skip | 8 |
OP | Control system...feedback, orbit correction, orthogonality etc., energy matching - 2 rings | 8 | 8 |
1 day | 2 days |
beam 1 | beam 2 | Total Time both rings |
|||
OP/MA | Incorporate FiDeL predictions, ramp mechanics: RF, Power Converters. First ramping attempts with single beam. cycling - all mechanics should have been tested before. | 24 | should follow | 24 | 48 |
BI | Commission beam instrumentation acquisition in ramp: orbit, tune, chromaticity, coupling | 8 | 8 | 16 | 16 |
OP | Orbit feedback | 8 | 8 |
||
PO | Tracking between sectors - first look | 8 | 8 | 16 | 16 |
3 days | 4 days |
fast track | Total Time both rings |
||||
OP/MA | Incorporate FiDeL predictions, mechanics. Load RF, Power Converters | 24 |
|||
BI | Commission beam instrumentation acquisition in ramp: orbit, tune-PLL, chromaticity, coupling | 16 |
|||
OP | Orbit feedback | 8 |
|||
PO | Tracking between sectors | 24 |
|||
BT | Commission beam dump in ramp | 48 |
|||
BI | Commission BLMs - energy tracking of thresholds | 8 |
|||
RF | Commission RF: frequency, voltage, dampers | 16 |
|||
OP | Measurements at intermediate energy | 16 |
|||
OP/AP | Measurements at 7 TeV | 24 |
|||
8 days |
Total Time both rings |
||
OP | Incorporate FiDeL predictions, mechanics. Load RF, Power Converters | 8 |
OP | Commission separation bumps in ramp | 8 |
OP | Orbit feedback | 8 |
PO | Tracking between sectors | 8 |
BT | Commission beam dumps in ramp - multiple ramps | 16 |
Check RF, BLMs, Instrumentation, correction strategies | ||
OP/AP | Measurements with 2 beam at 7 TeV | 24 |
3 days |
Total Time both rings |
||
COLL | Collimation setup | 24 |
OP | Separation bump reduction, interaction with orbit feedback: points 1 & 5 | 16 |
BI | Commission luminosity monitors | 8 |
OP | Establish collisions | 8 |
2 days |
ML May 2006