Week 29: Machine coordinators: Mike Lamont (We-Mo), Ralph Assmann (Mo-We),
Eva Barbara Holzer
Day |
Summary |
Link to report from morning meeting |
Monday 25th July
|
|
8:30 meeting |
Sunday 24th July
|
-
Fill 1970 - 1974
- hours in stable beams:
1:37+1:08+0:46+0:00+5:15
- Luminosity: 9.5+6.2+4.4+0+25.5 pb-1
- beam dumps by:
- Vacuum spike 4L8
- Controller IT5 - Possible SEU
- Cryo – R1 24V supply - Possible SEU
- QPS communication problem
- Electrical network glitch
|
9:00 meeting |
Saturday
23rd July |
- Fill 1967 11:26 hours in stable beams; luminosity
delivered: 42 pb-1; dumped by cryo
- Fills 1968 - 1971: total of 3:31 hours in stable beams;
luminosity delivered: ~20 pb-1; dumped by:
- 2 time BLM TCTVB.4L8 due to vacuum
activity
- EDF electrical network glitch
- Cryo sector 56
|
9:00 meeting |
Friday 22nd July |
- 14:30 - 23:01 fill 1966 stable beams: 2.3 – 2.4 microns
into collisions, 1.57e14 total per beam, 1.14e11 per bunch,
~ 1.55e33 cm-2s-1
- PS/LEIR intervention and Booster MPS problem
- 02:00 fill 1967 stable beams: bunch currents ~1.11e11,
Initial luminosity ~1.45e33
- beam aborts/interlocks: cryo intervention, CMS
BCM2, RF HOM temperature, ventilation doors communication.
|
8:30 meeting
|
Thursday 21st July
|
- Fill 1962 for 15:26 hours in sable beams; luminosity
delivered 46/44 pb-1
- switching e-cloud solenoids off for cleaning
- no beam from SPS (MKD problem 17:30 - 22:30)
- beam abort/interlocks give by: CMS BCM (no data on both
optical lines for 2.5s); RF spark; injection losses B1 MSIB;
QPS on RQTF.A67B1 (tune feed-back during squeeze);
communication lost of ventilation doors; power converter
RCBXH1.R1
|
8:30 meeting |
Wednesday, 20th July |
- Back in business after access for DFB controller fix (possible SEU)
- 12:50 Stable beam - fill 1961 - initial lumi > 1.4e33
- 15:00 fill 1961 lost to worldFIP repeater problem in sector 81
- Access required
- Back in Stable beam by 22:30 - fill in overnight
|
8:30 meeting |
Tuesday, 19th July |
- beam back during the evening/night
|
8:30
meeting
|
Monday, 18th July |
- 03:42 Fill #1955, 1092b, stable beams
- 09:50 Beams dumped, trip of RQTL7.L7B1
- Fills #1956 - #1958, 1380b: 20 minutes
stable beams
- 22:39 cryo lost: beam back Tuesday
evening/night
|
8:30
meeting
|