Performance 2016

2016 should be a standard long year:

  • ~150 days of proton physics including intensity ramp-up (down from 160 at start 2016 following schedule review)
  • Intensity ramp-up - assume 4 weeks
  • Planning on nominal 25 ns beam from the injectors - figures based on 2015 experience shown below
  • Usual caveats apply - integrated totals will be largely driven by availability.
  • BCMS in 2015 tested but compromised by presence of e-cloud - consider as back-up option to be explored further in 2016

Assumed parameters

Parameter Chamonix 16 Actual - July 16 - BCMS  
Energy [TeV] 6.5 6.5  
Bunch spacing 25 ns 25 ns 288 bunches per injection following TDI replacement
β* (1/2/5/8) [m] 0.4 / 10 / 0.4 / 3 0.4 / 10 / 0.4 / 3 Tested in 2015 - 0.5 m also an option
Ext. half X-angle (1/2/5/8) [μrad] -185 / 200 / 185 / -250 -185 / 200 / 185 / -250 10 sigma in 1&5 assuming 3.75 micron emittance
Number of colliding bunches (1/5) 2736 nominal 25 ns 2076 Limited by SPS dump to 96 bpi as of July 16
Bunch population 1.2e11 1.18e11  
Emittance into Stable Beams [μm] 3.5 2.6  
Bunch length [ns] - 4 sigma 1.25 1.05 Start of fill
Peak Luminosity (L0) [cm-2s-1] 1.1e34 1.1e34 BCMS could give around 1.4e34
Peak mean pile-up (inel xsection 80 mb) 29 39 cf. ~40 with BCMS
Average mean pile-up ~25 27  
Average luminosity lifetime (tau) 20 hours 24 hours  
  • Taking the fill length distribution from 2015 - phase 2 25 ns ramp-up (56 days)
  • fit to an Erfc
  • taking the product with L0exp(-t/tau) - values above
  • scaling from 56 (2015) to 150 (2016) days and factoring in the ramp-up (3-4 weeks)
  • one gets around 31 fb-1 for the year
  • (As a rough consistency check - naive application of 2012's Hubner factor (0.18) gives 26 fb-1 for the year).

Time in Stable Beams:

Assumption at start of year:

  • the 2012 physics efficiency was around 37%.
  • A number of issues affecting this number have been addressed (e.g. R2E, vacuum non-conformities), however running at 6.5 TeV brings additional challenges (hardware nearer limits, lower tolerance to beam loss etc.). 25 ns brings e-cloud, higher UFO rates.
  • It would seem reasonable at this stage to assume a similar physics efficiency for 2016. Thus 0.37*150 days = 55.5 days = 4.8 million seconds.
  • Operation in 2015 seems to support this assumption - reasonable availability despite being a commissioning year and having to face virgin e-cloud and UFOs. We had around 32% physics efficiency during phase 2 of the 25 ns ramp-up.

Update 29th July 2016

  • Astounding availability and few premature dumps From just after the first technical stop we have enjoyed 84% availability combined with very few premature dumps. To 22 July - 67% time in Stable Beams (physics efficiency).
  • As of 29th July - around 72 days proton physics left (the possibility of dropping a week is to be discussed). The rest of the year is somewhat choppy (MD, technical stop, special physics runs) - let's assume 60% physics efficiency: another 3.7 million seconds.
  • Since 11 June: 15 fb-1 delivered - around 340 pb-1/day.
  • Assuming 60% Stable Beams and similarly availability gives ~20 fb-1 additional integrated luminosity between 1st August and 1st November.

 

 

Updated July 2016 - Mike Lamont