From 3.5 TeV to 4 to 5 TeV. On the list:
Task | Comment | Time estimate |
Hardware commissioning of main circuits to higher energy |
|
~2 weeks |
Qualification of machine protection to higher energy without beam | FMCMs, PIC, Collimators, TCDQ, BLMs, BPM interlocks, SMPs, RF, LBDS | In parallel with HWC |
Operations dry runs of qualified sectors | Ramp, squeeze to/at higher energy | Sector by sector - after hand over from HWC |
Re-commissioning of ramp and associated machine protection appropriate to the higher energy | With safe beam. Machine protection: LBDS, BLMs, RF | ~1 week |
Re-commissioning of squeeze | Could possibly ramp-squeeze-ramp which would avoid the need of recommissioning the 3.5 TeV squeeze. | |
Optics and operations checks at high energy | ~2 days | |
Re-optimisation of collimators | ~4 days |
Possible Strategy
ML August 09