Date
|
Summary
|
Link to report from morning meeting
|
Monday 16 July |
- 07:00 ongoing ... stable beams
|
8:30
meeting |
Sunday 15 July |
- 05:04 RQTL11.L1B2 trip, beams dumped. Int lumi 113 pb-1
- 06:39 Ramp fill #2844
- 07:13 Dump in adjust, Loss of CM for AML7 tripped S67.
Access of ODH.
- 08:50 Closing machine
- 10:00 injection & ramp: beam dump: pc fault (RQTl10.L7B1)
- 12:20 injection & ramp: beam dump: BLM alarm
- 16:00 injection, ramp, squeeze, stable beams
- 21:40 beam dump: trip of RCBXV2.R1
- 22:30 injection, ramp, squeeze, stable beams
|
9:00
meeting |
Saturday 14 July |
- 00:38 Beam dump: suprious trigger on collimator TCTH.4R5.B2
- 02:54 New injection
- 04:01 Dump during adjust: beam loss alarm
- 05:34 Injection, ramp, squeeze, adjust
- 06:58 Stable beams fill #2842
- 18:30 Operator Dump, Int. Lumi 147 pb-1
- 21:17 Stable beams, fill #2843, init lumi 5.9/5.6e33 cm-2s-1
|
9:00
meeting |
Friday 13 July |
- 07:14 Trip of IT-R5 just before programmed dump, end of RP fill.
- 09:22 Injecting again.
- 09:35 No beam from SPS followed by transfer line steering
- 12:12 Start ramp
- 12:58 Beam dumped, while going into collision, by trip of IT.R5,
again
- 13:49 Access for EPC
- 15:42 Start pre-cycle, but first put IT.R5 at 4 TeV settings for a
while
- 16:00-19:00 SPS problem, no beam
- 20:00h injection & ramp ... but dump due to rf crowbar
- 21:30 injection, ramp & squeeze
- 23:20 stable beams !!!
|
8:30
meeting |
Thursday 12 July |
- 00:08 ramp for 90m optics run: beam dump due to IR6 BPMs
- 02:31 injection & ramp
- 03:55 beam dump due to COD settings
- 06:04 injection & ramp: bam dump QPS trigger RSD1.A45.B2
- 09:25 another ramp for 90 m optics run: beam dump due to collimator
energy threshold function interpolation
- 10:39 RSF2.A34B1 tripped at injection settings: access for EPC to fix.
In parallel access for QPS
- 12:41 Phantom of the ventillation doors passed by in Pt 2 (UL26)
- 13:11 Door closed
- 13:56 No beam from SPS, RF problem needing an access.
- 15:46 Injecting again.
- 17:09 Ramp for 90 m physics run started.
- 18:10 Stable beams fill #2836
- 18:30 Roman Pots in.
|
8:30
meeting |
Wednesday 11 July |
- 04:14 ATS beam dumped
- 05:05 Injection probe for beta* levelling MD
- beta* leveling tests with upto 36 bunches
- 12:41 beam dump due to transverse instability at VdM scan
- 15:04 injection for 90m optics: loss maps
- 22:30 loss maps ok, injection for 90m physics run
- injection problems: IQC latches beam 1
|
8:30
meeting
MD
Summary |
Tuesday 10 July |
- 01:58 Second ramp for high pile-up MD, high losses B1, longitudinal
blow-up not working for B1, dump before collisions
- 03:51 Third ramp for high pile-up MD, B1 longitudinal blow-up working
at end of ramp.
- 06:29 Fourth ramp for high pile-up MD. Long. blow-up OK. Pile-up of 65
(CMS) and 70 (ATLAS).
- 07:36 Dump after high pile-up MD.
- 08:09 Lost Cryo matching section R8 ('warm bubble').
- 09:16 Cryo back, pre-cycle.
- 10:04 Start of 25 ns injection MD. Injecting probe. Successfully
injected 288 b for B1 and 144 b for B2. 288 b stable with high
chromaticity.
- 13:15 End of 25 ns MD. Start pre-cycle for ATS MD.
- 14:27 Injection of first ATS probe.
- 16:09 First ATS ramp. The intensity was lost when trimming the RF
frequency for dispersion measurements. 2 fat pilots were in originally.
Operator dump.
- 18:46 Second ATS ramp followed by squeezing.
|
8:30 meeting |
Monday 9 July |
- 02:00 Cryo revovery starting.
- 16:20 Cryo ok, restart machine
- 17:40 injecion for Q20 beam, high pile up studies.
- 21:00 injected intensity: 3*10^11 in one bunch
- 22:14 First ramp for high pile-up MD, instabilities during ramp &
squeeze
|
8:30 meeting
|