Date
|
Summary
|
Link to report from morning meeting
|
Monday 9 July |
- 02:00 Cryo recovery starting.
|
8:30 meeting |
Sunday 8 July |
- 02:55 ATLAS toroid back up to nominal current
- 05:27 Beam dump, lost to electrical perturbation visible on several power converters. FMCM triggered first for RD1.LR5. 144 pb-1 in 11 hours 51 minutes of stable beams
- 06:16 filling again
- 06:53 Thunderstorm. All sectors apart from sector 12 trip.
- Access for QPS.
- 10:30 Problem with LBDS B2. PLC lost communication to
some HW (kickers). Access.
- 15:00 Filling.
- 17:00 Beam lost at end of squeeze, large losses on B2.
- Refill...
- 19:40 Stable beams fill 2819 Initial luminosity 5.8 e33 cm-2s-1
- 20:50 Beam dumped, RF B2 due to cryo problem R4.
Integrated 22 pb-1.
- Cryo problem R4, valve blocked.
- 23:00 Access for cryo.
|
9:00 meeting |
Saturday 7 July |
- 00:30 Colliding at 90 m.
- 00:50 Both IR1 and IR5 optimized.
- 02:20 TCTs are aligned, start of RP alignment.
- 05:00 Beams dumped on wrong manipulation with RP of TOTEM, dump on
IR5 BLMs.
- Refill for 90 m.
- 08:30 Back in collisions at 90 m.
- 08:45 ATLAS magnets ramp down.
- 10:00 Start RP/collimator setup.
- 13:10 loss maps
- 14:10 Access for ATLAS (CMS in as well)
- 16:00 Injecting for physics
- 17:35 Stable beams fill 2816 Initial luminosity 5.9 e33 cm-2s-1
|
9:00 meeting |
Friday 6 July |
- 02:20 Injecting again
- 03:30 Stable beams fill 2812
- 03:55 RB.A45 tripped QPS current loop is open and seems that the current (normally 50 mA) is 0.
- 09:10 QPS problem fixed by piquet
- pre-cycle
- 12:00 Filling 3 bunches for 90 m setup.
- 14:00 Beams were colliding immediately, but unfortunately the
colliding bunches became unstable and were lost (again B2). Finished
some measurements with the remaining bunches.
- 15:00 Ramp down.
- 16:00 Access for ATLAS safety system - sniffer problem. Water leak
in US15, some crates under water (eg vacuum).
- 21:30 End of access. Precycle.
- 22:45 Prepare for injection, fill 2814.
|
8:30 meeting |
Thursday 5 July |
- 02:00 One of the 2 warm cryo compressors of Pt2 stopped (oil leak).
- 09:00 Cryo intervention in Pt2 (compressor) during stable beams.
- 10:15 Beam dumped QPS on Q5.L1, integrated L 143 pb-1.
- Access for ALICE, Cryo, ADT
- 15:00 Filling, 1.5E11 ppb.
- 16:10 Beam lost when going into collisions - again! Selected B2
bunches lost.
- 17:00 Injecting probes for test ramp & squeeze for chromaticity measurement
- 19:05 injecting for physics – slightly reduced bunch currents
- 21:10 Stable beams Fill 2810
- 21:15 Beams lost just after going into stable beams Lost sector 12 – thunderstorm some time before we could close the switches for the RB.A12 Precycle
- Midnight – injection again
- 01:30 Beam lost going into collisions (fill 2811) Bit different this time Losses in IP7 a few seconds from the end of the collision BP
|
8:30 meeting |
Wednesday 4 July |
- 06:00
Beam dumped by OP, integrated L 70 pb-1.
- Moving on to 1380 bunches, lower intensity.
- Losses starting on some bunches of B2 during the squeeze, holes in
some batches, corresponding B1 bunches blown-up in H.
- 09:30
Stable beams fill 2806, 1874b, 4.6E33
cm-2s-1.
- TCL scans by the collimation team while Fabiola is speaking...
- 18:40
Beam dumped by OP, integrated L 103 pb-1.
- Injection, B1 (6b) dumped twice on TDI, SPS RF not locked to LHC RF.
- 00:10
Stable beams fill 2807, 1874b, 6.2E33
cm-2s-1.
|
NO 8:30 meeting |
Tuesday 3 July |
- 00:53 lose 2799 in the squeeze trip of RQ7.L7B1 – QPS trigger
- 02:00 Back around at injection 03:38 Fill 2800 - beam dumped by high losses on Q4.L6 on RS 5.2s after 1 minute into the collisions BP. Tune signal for beam 1 show instabilities in H
- 05:30 Access start for Atlas turbine – Torroid rack
- 07:10 Atlas finished
- 08:10 Lost test ramp to un-masked interlocks.
- 09:30 New test cycle for Q' measurements.
- 11:30 Test beam dumped by too large RF frequency trim.
- 13:00 Injecting for physics.
- 14:30 Beam dumped when going into collisions with 852b, losses on
B2.
- 16:00 New attempt with 852b with lower intensity
- 17:45 Beam dumped once more when going into collisions with 852b,
losses on B2.
- Reverting some Q' trims, trying with 840b scheme.
- 18:30 Refill with 840b, lower intensity.
- 20:55
Stable beams fill 2805, 840b, 3.5E33
cm-2s-1.
|
8:30 meeting |
Monday 2 July |
- 07:00 Stable beams fill 2797, 480 bunches, 3E33
cm-2s-1.
- 14:00 Beam dumped by OP, integrated L 38 pb-1.
- Access for EE switch RCS.A23.B1.
- 14:00 Solenoids around injection kickers switched back ON.
- Precycle.
- 17:30 Injecting.
- 19:20 Stable beams fill 2798,
852b, 4E33
cm-2s-1.
- 20:00 Beam dump, UFO at MKI2,
integrated L 7 pb-1.
- Access prepared for LHCb.
- 22:00 Access finished ready for injection
|
8:30 meeting
|