Week 16: Machine
coordinators: Jan Uythoven, Ralph Assmann
Plan for the week: Finish
intensity ramp-up, stable beams, MD period
Date |
Summary |
Link to report from morning meeting |
Monday 23 April |
|
|
Sunday 22 April |
|
|
Saturday
21 April |
|
|
Friday
20 April |
|
|
Thursday
19 April |
|
|
Wednesday
18 April |
|
|
Tuesday
17 April |
|
|
Monday 16 April |
·
Power
converter problem, access needed ·
06:30
prepare injection for VdM scans. ·
08:17
Injection. Programmed dump at injection, due to low bunch intensities for VdM scan (several bunches at 5e10, which is too close to
the BPMSW threshold of 4e10). Alice solenoid tripped (low gas/water pressure
in the solenoid), ramping back up. Refill. ·
12:44
Ramp fill for vdM scan. ·
13:41
Stable beams. ·
14:05
vdM scan starting. ·
14:21
RCBV17.R7B1 tripped and was caught by the SIS. The orbit was growing and we
would have dumped on the excursion otherwise. No error in the PIC history
buffer for this circuit. ·
At
collision settings without beam, Daniel V updated abort gap cleaning
parameters. ·
14:59
Rampdown and preparing for access for ALICE. ·
16:43
Injection. ·
17:57
Ramp fill for vdM scan. ·
18:34
Stable beams. vdM scans starting. |