Day
|
Summary
|
Link to report from morning
meeting
|
Sunday 22nd August
|
- Recovery from cryo problem in Pt5.
- 04:00: Glitch on electrical network
results in several trips.
- Morning: recovery from network glitch.
- Rest of the day: Physics fill with 48 bunches per beam.
|
Slides
from 9h meeting |
Saturday 21st August
|
- Recovery from cryo problem in Pt6. No beam before Saturday evenin.
- 22:00: Preparing new physics fill with
48 bunches. Lost due to another Cryo problem in Pt5.
|
Slides
from 9h meeting |
Friday 20th August
|
- Morning: Continuation of physics fill
from night.
- Noon: Potential for end-of-fill
studies (Damper).
- 5pm: Cryo problem in Pt6. No beam
before Saturday noon.
|
Slides
from 8h30 meeting |
Thursday 19th August
|
- Morning: access for various issues.
- Noon: Problems with injector complex
(no beam for several hours).
- Afternoon: Injection setup for 48
bunch per beam
- Night: Physics fill with 48 bunches
per beam.
|
Slides
from 8h30 meeting |
Wednesday 18th August
|
- Morning to evening: Physics fill with
25b per beam.
- Late evening: Short access to repair
quench heater power supply.
- Night: Physics fill with 25b per beam.
<>>
|
Slides
from 8h30 meeting |
Tuesday 17th August
|
- 9:00 - 11:00 :
LHC and SPS preparing machine and beam parameters for the first tests
for bunch train operation (1 train of 4 bunches, each separated by 150
ns)
- 11:00 - 14:00 : Injection tests of 1
train of 4 bunches
- Fill for physics
|
Slides
from 8h30 meeting |
Monday 16th August |
- 09:00 - 11:00 : EOF (ADT and Roman Pots in)
- 11:00 : Dump beams
- 11:00 - 13:00: Ramp down + new BLM firmware release (dry
tests)
- 13:00 - 16:00: LHC in access
- 16:00 - 20:00: LHC recover 450 GeV injection conditions
- overnight: BLM requalification tests and test ramp
|
Slides
from 8h30 meeting |