| Day | Short
summary/plan | Link to reports from 8:30 and 17:00
meetings | 
    
      | Monday 21st June | 
		Midnight - 3:00 : Controlled beam scraping before asynchronous beam 
		dump.3:00 - 5:00 : Combo ramp down5:00 - 13:00 : 450 GeV LBDS setting-up and qualification13:00 - 15:00 : Combo ramp down15:00 - 01:00 : Inject 2bx2b (single_2b_1_1_1), ramp, squeeze, 
		collapsed separation bumps, crossing angle IP1/5 at 
		-100/100 urad - protection device qualification to continue | Report from 08:30 meeting Serge Claudet presentation
 | 
    
      | Sunday 20th June | 
		Recover from access for FIP repeater in RR17~noon - midnight: Inject 2bx2b (single_2b_1_1_1), ramp, squeeze, 
		collapsed separation bumps, vernier scan, crossing angle IP1/5 at 
		-100/100 urad -  TCTs setting up at 3.5 TeV -TCDQ - midnight - 3:00 : Controlled beam scraping before asynchronous beam 
		dump. | Report from 09:00 meeting | 
    
      | Saturday 19th June | 
		~ 9:00 - 10:00 : Exercise the mechanics of collapsed bumps in all 
		IPs, switching IP1/5 to -100 urad10:00 - 12:00 : Ramp down combo12:00- 16:20 : Inject 2bx2b (single_2b_1_1_1)for TCTs setting up at 
		3.5 TeV, collapsed separation bumps, with crossing angle IP1/5 at 
		-100/100 urad - dump beam due to LBDS internal fault (vacuum interlock)16:20 - 17:30 : Continue with beam1 to experience controlled beam 
		losses on the 3rd resonance. Lost beam 1 due to interlock BPM in IR617:30 - 20:30 : Ramp down combo - investigating collimator problem 
		(won't go to injection settings)Overnight : Refill and inject + ramp + squeeze + collapse bumps +  Vernier scan 
		done at the exception of IP8 (and partially in IP2) | Report from 09:00 meeting | 
    
      | Friday 18th June | 
        05:00 - 14:00 : Beam preparation for TCT setting-up but at 9:00, trip on RB.A78 - 
		Investigation and recovery - 
		Collimator sequence tests - Damper checks14:00 - 15:00 : Damper tests with beams at 450 GeV for multi-bunches15:00 - 18:30 : Beam preparation for the next TCT setting up but 
		beams were dumped at 3.5 TeV, squeeze at 7m due to trip of RB.A7818:30 - 00:00 : Ramp-down combo, access for RB.A78 - Pre-cycling - 
		Linac RF problem - PS septum problem delaying the beam re-start00:00 - 02:00 : Preparing for optics measurements from injection to 
		3.5 TeV, squeezed optics.02:00 - 09:00 : Chromaticity measurements during the ramp and beta 
		beat measurements during the squeeze - exercise  collapse of all 
		separation bumps and bring crossing angle in IP1/5NO 17:00 meeting | Report from 08:30 meeting | 
    
      | Thursday 17th June | 
        ~midnight - 4:00 : Controlled longitudinal blow-up, 450 GeV, 
		multi-bunches4:00-9:00 : Beam preparation for the next collimation setting up at 
		3.5 TeV, squeeze to 7m9:00 -11:30 : Collimator setting-up at 3.5 TeV, squeeze, 7 m, then 
		3.5 m, with separation on. Lost beam 1 while moving the collimators and 
		lost beam 2 due to trip of RSD2.A56B1.11:30 - 13:30 : Ramp-down combo 13:30 - 14:30 : Access for FIP communication in UA4314:30 - 17:00 :  Recovering from access17:00 - 21:00 : Beam preparation for the next collimation setting up 
		at 3.5 TeV, squeeze to 7m21:00 - 03:00 TCT collimator setting-up at 3.5 TeV, squeeze, 7m, 
		then 3.5m, with separation on,TCT setting-up - TCDQ setting-up03:00 - 5:00 : Ramp-down combo - Test run with new collimator 
		settings during the ramp - squeeze to 3.5 m - TCTs 
		setting-ups - TCDQ set-up - Qualification 1 if beams survive.NO 17:00 meeting | Report from 08:30 meeting | 
    
      | Wednesday 16th June | 
        ~midnight - 6:00 : Inject-Ramp-Squeeze for operational checks7:00-9:00 : access for world FIP repeater problem on 60A correctors 
		in S789:00-18:00 : Pre-cycle and beam preparation for the next collimation setting up 
		- lost beams due to tune feedback - re-doing the whole exercise18:00 -22:00 : collimator setting-up at 3.5 TeV, un-squeezed, with separation 
		on, 1e11/beamOvernight : Controlled longitudinal emittance at 450 GeV, 
		multi-bunchesNO 17:00 meeting | Report from 08:30 meeting | 
    
      | Tuesday 15th June | 
        23:00 - 4:00 : Squeeze commissioning to 3.5 m4:00 - 4:30 : Beta beat measurements at 3.5TeV, 3.5m - Cancelled - 
		no AC dipole4:30 - 7:00 : Ramp down combo + RF access in UX457:00 - 11:00 : Controlled longitudinal emittance blow up during the 
		ramp, 1e1111:00 - 15:00 : Ramp-down combo and preparation for collimator setting-up at 3.5 TeV, 
		10m, 1e11/beam, separation onuntil midnight : collimator setting-up at 3.5 TeV, unsqueezed, with separation 
		on, 1e11/beamNO 17:00 meeting | Report from 08:30 meeting | 
    
      | Monday 14th June | 
        12:00 : intervention for the cryogenics system finished12:00 - 18:00 : Pre-cycle, inject, prepare for high bunch intensity studies18:00 - 21:00 : Transverse damper commissioning during the ramp21:00 - 23:00 : Ramp down comboTHERE WILL BE AN 17:00 MEETING TODAY | Report from 08:30 meeting Report from 17:00 meeting
 |