Objectives
Multi-system tests to check integration and readiness of all systems involved in a given phase of LHC operations. The aim would be to check the functionality of the individual systems before attempting to drive them in a coordinated way to test interdependencies etc. In particular:
- Check the beam instrumentation acquisition chain
- Check all equipment control functionality
- Check timing and low synchronization
- Check functionality of the control system from the control room high level
applications. One key goal is to drive everything using high level application software from the CCC.
- Drive all relevant systems in a synchronized way through the standard operational
sequence
- Check machine protection and interlock systems
Organization
- Coordinated by Operations. Preparations for, and results of, dry runs to be discussed at LHCCWG.
- In close collaboration with equipment groups, technical issues to be discussed in ABCIS meetings.
- Seen as a prelude to full system tests to be performed before beam.