LHC 2013 - latest news

Week 2: Machine Coordinators: Bernhard Holzer, Jan Uythoven

Goal of the week: recovery from 2012/2013 Christmas Stop.

Proton-lead run scheduled to start 14th January.

p-Pb commissioning plan (John Jowett)

Date

Summary

Link to report from morning meeting

Mon 14 Jan
  • 02:20 beam loss due to instabilities
  • 03:15 new injection
  • 04:25 beta sqeeze, 80cm reached, optics checks.
08:30 meeting
frduval
Sun 13 Jan
  • 00:20 Cryo conditions back
  • 01:30 UPS repair ongoing
  • No beam before this evening
  • 23:45 repair work done & checked, beam injection for beta squeeze
09:00 meeting
Sat 12 Jan
  • 01:00 - 05:00 squeeze in steps down to 80cm
  • 05:42 Dump beam at 4 TeV, end of beta beat measurements over squeeze
  • 06:48 Start TDI alignment following intervention on TDI during TS
  • 13:30 TDI alignment finished successfully
  • 13:30 Start of BPMS interlock check after installation of new attenuators during TS
  • 16:30 Interlock checks finished successfully
  • 16:30 Check of BPMS intensity limit with  a single bunch: 1.5e9
  • 17:30 Start check of BPMS with bunch trains at injection
  • 19:15 Mains perturbation, cryogenics lost... and a lot more
  • 22:03 Confirmation that an electrical rack has caught fire in RE88, UPS damaged
09:00 meeting
Fri 11 Jan
  • 00:48 All HWC tests finished
  • 02:41 BIS loops closed, pre-cycle
  • 06:50 RF conditioning M1.B1 finished
  • 08:00 Access for pc replacement & RF low level set-up
  • 15:20 injection of one proton bunch (beam1) and one ion bunch (beam2)
  • wrong bucket number due to SPS BQM settings
  • test ramp p-Pb
  • 16:30 4TeV reached successfully
  • beam dump to check dump system
  • 21:00 new injection, three p-bunches for squeeze test and beta beat measurements
08:30 meeting
Thu 10 Jan
  • Cryo cooldown ongoing
  • 09:30 Network routers restart, all went just fine.
  • 12:00 All power converters from the arcs on at standby
  • 12:00 ELQA test finished
  • Circuit tests
  • Still some selected accesses
  • 17:40 Cryo Maintain OK for all sectors
  • 18:37 Cryo OK complete machine
  • Test of circuits and QPS
  • 22:55 All vacuum valves open

Status Cryogenics (S. Claudet),
Status End Technical Stop (K Foraz),
Restart plan (J.Jowett),
Router restart (E.Martelli)

Wed 9 Jan
  • Cryo cooldown ongoing
  • Machine in  access
  • End of Technical Stop, machine handed over to OP
No 8:30 meeting
Tue 8 Jan
  • Machine in access
  • Cryo cooldown ongoing
Status Cryogenics (S.Claudet)
Mon 7 Jan
  • Machine in access
  • Cryo cooldown ongoing
No 8:30 meeting