Week 35: Machine coordinators: Jan Uythoven and Jorg Wenninger
TS coordination by J. Coupard
TS, recovery from TS, 1 m beta*, Alice polarity change
Day |
Summary |
Link to report from morning meeting |
Monday 5th September |
|
|
Sunday 4th September |
|
|
Saturday 3th September |
· 02:45 First ramp after technical stop · 06:45 Problems with SPS extraction kicker, no beam for collimator alignment · 10:30 Beam back · 12:00 Ramp and squeeze for TCT alignment. Loss spikes delaying start of alignment, traced to RT trims being enabled for the FBs (despite FB being OFF). · 14:30 TCT alignment starting with separated beams. · 19:00 TCT alignment done. Loss maps and asynch. dump test with TCTs at 11.8 sigma. · 00:00 Fill 1 probe/beam for aperture measurements. TCTs in IR1+5 with new functions. |
|
Friday 2th September |
· TS Day 5 · 14:30 Cryo Start back for all powering sub-sectors. · 16:00 Evacuate machine & experiments · 17:00 Last searches · 19:00 End of technical stop · 22:50 Beams injected |
|
Thursday 1th September |
|
|
Wednesday 31th August |
|
- |
Tuesday 30th August |
|
|
|
||
Monday 29th August |
|