Overview - LHC commissioning strategy with beam 2010

Update May 2010

The squeeze to 2 m. in all experiments' interaction points has been commissioned and stable beams at the safe beam limit is now more-or-less routine.

The next month or so will be spent fully qualifying the machine setup and procedures for higher intensities. The first two planned increases in intensities are to a total single beam intensity of a round 1 e11 and then double this - this should take a month or so. The total single beam energy will then be around 100 kJ. Any further increase will demand that we really have the machine protection system. collimation, beam dump system and operational procedures fully nailed down.

 

Strategy

  • Respect safe beam limits during initial commissioning phase - perform phased qualification of machine protection using very safe and safe beams before increasing intensity.
  • Re-commission essential systems and make necessary measurements at 450 GeV
  • Commission ramp to 3.5 TeV
  • Pilot collisions at 3.5 TeV unsqueezed
  • Commission squeeze to stage A target values
  • Establish "stable beams" at target squeeze values with beam intensity below Safe Beam Limit.
  • Full Machine Protection commissioning will need a well adjusted and well understood machine - hold full machine protection qualification until after first low intensity collisions

 

Energy Safe beam Very safe beam
450 GeV
1 e12
1 e11
1 TeV
2.5 e11
2.5 e10
3.5 TeV
3.1 e10
probe

 

Detailed planning is a deliverable of the LHC beam commissioning workshop

Plan Outline

Time estimate

Phase
Time [days]
Bunches
Intensity
Main tasks
Circulating beam
2
1
2 e9
essential checks, orbit, RF etc.
450 GeV recommissioning
7
1
5 e9

tune, Q’, C-, orbit, collimators, LBDS, instrumentation

450 GeV essential optics checks
3
1
5 e9

beating, energy matching

450 GeV - two beams
1
1
5 e9

bumps as standard set-up, adjust TDI etc

Ramp to 3.5 TeV
5
1
5 e9
commission essential machine protection, experiments' dipoles on in ramp, orbit and tune feedback
3.5 TeV measurements & MPS
7
1
5 e9
standard measurements plus machine protection checks etc.
Pilot collisions unsqueezed
3 - 5
2
5 e9 - 3 e10
safe beam at 3.5 TeV
Commission squeeze
4
2
5 e9
orbit and tune feedback, collimation, aperture, bumps, machine protection checks, beam dumps etc.
Pilot collisions squeezed - stable beams
7
2
5 e9 - 3 e10
safe beam

With optimistic machine availability. Note agreement to provide stable beams for collisions - this takes a long, careful time to set up.

ML January 2010