Overview - LHC commissioning strategy with beam 2009

The initial commissioning with beam in 2009 went well and a good sample of collisions at 450 GeV was provided to the experiments. The ramp to 1.18 TeV was commissioned and pilot collisions allowed the experiments to take some data at this energy.

Strategy

  • Go for collisions at top energy as soon as safely possible
  • Full Machine Protection commissioning will need a well adjusted and well understood machine
  • Perform phased qualification of machine protection using very safe and safe beams before increasing intensity.
  • Commission essential systems and measurements at 450 GeV
  • Move quickly into the snap-back and ramp
  • Hold full machine protection qualification until after first low intensity collisions
  • Respect safe beam limits during initial commissioning phase:
Energy Safe beam Very safe beam
450 GeV
1 e12
1 e11
1 TeV
2.5 e11
2.5 e10
3.5 TeV
3.1 e10
probe

The injector complex has defined the following beams:

  • LHCPROBE intensity range between 0.5-2E10 ppb and 1 bunch only. (<1 um/0.3 eVs)
  • LHCINDIV 2-12E10 ppb with 1-4 bunches (3.5 um/0.8 eVs)

Plan Outline

Would hope to get this far before the 2009 Christmas stop

Time estimate

Phase
Time [days]
Bunches
Intensity
Main tasks
Circulating beam
4
1
2 e9
capture, energy matching, initial RF commissioning
450 GeV commissioning
4
1
5 e9

tune, Q’, C-, orbit, collimators, LBDS, instrumentation

450 GeV essential optics checks
2
1
5 e9

polarities, response, beating

450 GeV - two beams
1
1
5 e9

bumps, instrumentation

450 GeV - collisions
2
12
1 e10

experiments on at 450 GeV

Snapback and ramp to 1 TeV
4
1
2 e9
orbit, tune (PLL), chromaticity
Ramp to 3.5 TeV
2
1
5 e9
commission essential machine protection
3.5 TeV checks & bring on experiments' magnets
3
1
5 e9
solenoids, dipoles, experiment related machine protection
First collisions
1
1
5 e9 - 2 e10
safe beam at 3.5 TeV
 
22

 

With optimistic machine availability - 1 month elapsed to establish first collisions at 3.5 TeV.

ML August 2009