Outline
Maximum energy and beta*s at each of the experiments to be established. |
With optimistic machine availability.
Phase | Time [days] |
Bunches |
Intensity |
Main tasks |
Circulating beam | 1 |
1 |
5 e9 |
essential checks, orbit, RF etc. |
450 GeV recommissioning | 2 |
1 |
5 e9 |
tune, Q’, C-, orbit, collimators, LBDS, instrumentation |
450 GeV essential optics checks | 0.5 |
1 |
5 e9 |
beating, energy matching |
450 GeV - two beams | 0.5 |
1 |
5 e9 |
bumps as standard set-up, adjust TDI etc |
Ramp to 3.5 TeV | 1 |
1 |
5 e9 |
commission essential machine protection, experiments' dipoles on in ramp, orbit and tune feedback |
3.5 TeV measurements | 1 |
1 |
SBL |
standard measurements - beating, coupling... |
Commission squeeze | 2 |
2 |
SBL |
orbit and tune feedback, collimation, aperture, bumps, machine protection checks, beam dumps etc. |
Full collimator set-up at 450 GeV, flat-top, squeezed and colliding |
7 |
2 |
nominal |
Including full validation - loss maps, asynchronous dumps |
Machine protection | 5 |
safe beam | ||
Beam dump set-up and validation | 4 - 5 |
2 |
nominal |
including async dumps. 12 - 14 shifts requested with beam |
Injection set-up | 5 |
various |
Looking towards 75 ns, can be staged |