LHC 2013 - latest news

The first 6 weeks of 2013 were devoted to a proton-lead run. Four weeks of magnet tests led into long shutdown 1 (LS1). During LS1 there will be consolidation and upgrades of all major systems. One principal activity is the opening of all magnet interconnects, the measurement of the resistance of all splices in the cables that carry the current between the main dipole and quadrupole magnets, and the repair of any non-conformities.. There are around 10,000 splices in all.

Recommissioning with beam is foreseen for the start of 2015.

 

During operations with beam, there is a meeting every morning (8:30 during the week, 9:00 Saturday and Sunday). A record of theese meetings can be found below.