Outstanding - October 2008
- Planned machine checkout 2009, requalification etc
- Machine commissioning 2009: dry runs, injection tests...
- Planned machine protection tests, requalification
- Commissioning organisation - was it optimum? How will it work coming out of shutdown?
- Testing limitations and how to get around them (energy tracking, LBDS, BIS, prepulses...).
Controls
- CO infrastructure stability: FESA, CMW, logging, JMS, timing etc
- BIS: full deployment, SMP
- Data management
- RBAC and MCS deployment & testing
- log exact timing events
Software
- Sequencer
- Post mortem with beam
- Triggered data acquistion
- Logging fundamental data
- Injection Quality Checks
- Injection Sequencing
- FIDEL - beyond 450 GeV
- Lumi scans, calibration etc.
- On-line model - status, improvements, uses
- Precision & Limits - deploy and test in LSA
- Test environment
- Trim bucket number
- Tidy up pc commands in equipstate
- CTRIM - time
Settings
BI etc
- Schottky
- Luminosity monitors
- Feedback - real time tests etc.
- Abort Gap Monitor - Abort gap cleaning
- BLM - threshold, management, reliability
- Grab ZDC from CMS
Hardware systems
- Shutdown activites: Injection, LBDS, Collimators
- MKQA, AC dipole
- RF & transverse damper: planned deployment and tests before beam
- RT behaviour of correctors - dig out what we did with Steve
- RT test
- QX alignment
Operations
- Operability of access systems - potential improvements
- Operational envelope limitations (energy, intensity, emittance, filling pattern).
- Preparing for injection more effectively (or just EIC training?). - procedures
Wiring - database or otherwise
- Check RCBYHS4.L8/R8 and warm corrector replacement
- Check sign of RCBYHS5.L2B1 (Q5 is turned)
- BPMWB.4L7.B2 - wrong (BPMW.4L7.B2 check)
- MO missing in sector 34 - 2/13 - beam 1 & beam 2
- QS missing in sector 34 - RQS.R3B1 (2/2) and RQS.A34B2 (2/4)
Experiments
Mike Lamont - last update Jan 09