LHC Commissioning with Beam

Re-commissioning with beam in 2011 started on 19th February. It took around 3 weeks to restablish collisions for the experiments. This was followed followed by a phased intensity increase in 1380 bunches per beam - progress outlined in the table below.. 2011 (& 2012) schedule available here

2011 - progress

Date
Bunches/beam
Colliding bunches
(Atlas & CMS)
Luminosity cm-2s-1
5th November
Switch to ions (fully stripped lead)
26th October
1380
1331
3.65e33
13th September
1380
1318
3.3e33
7th August
1380
1318
2.1e33
28th June
1380
1318
1.25e33
24th June
1236
1180
1.26e33
29th May
1092
1042
1.26e33
23rd May
912
874
1.1e33
1st May
768
700
8.4e32
27th April
624
598
6.7e32
21st April
480
424
4.67e32
16th April
336
322
3.57e32
14th April
220
214
2.28e32
24-27th March
1.38 TeV run (followed by technical stop and scrubbing)
22nd March
200
194
2.5e32
  • 13th March: First stable beams, 3 bunches per beam, initial luminosity 1.6e30 cm-2s-1
  • 5th March: nominal bunches at 3.5 TeV, start collimator set-up program
  • 3rd March: first collisions at 3.5 TeV, beta*=1.5 m. with pilot beams
  • 19th February: First beam, circulating beams established.

2010 - progress

Restarted with beam 27th February 2010. First collisions at 3.5 TeV took place on 30th March 2010. End of run on 6th December 2010.

Date
Bunches/beam
Colliding bunches
Luminosity cm-2s-1
15th November
121
113
2.88e25
9th November
17
16
3.5e24
4th November
LHC switched to heavy ions (fully stripped lead)
25th October
368
348
2.07e32
16th October
312
295
1.35e32
14th October
248
233
1e32
8th October
248
233
8.8e31
4th October
204
186
7e31
29th September
152
140
5e31
25th September
104
93
3.5e31
23rd September
56
47
2e31
22nd September
24
16
4.6e30
1st - 22nd September
Bunch train commissioning
29th August
50
35
1e31

    Stage A: Initial commissioning with a single bunch per beam moving towards 43 bunches on 43 bunches (moving to 156 on 156) with moderate intensities. First collisions un-squeezed; followed by partial squeeze.

    Progress on initial commissioning below.

Stage A - progress 2010

Phase

Schedule/Progress
Notes

Ring
factor

Total Time [days]
both rings

Comments

A1

Injection and first turn

First turn

2

4

Complete - end Feb

A2

Circulating beam

Circ. beam

2

2

Complete - end Feb

A3

450 GeV initial commissioning

450 GeV prelim 

2

4

Complete - start March

A4

450 GeV optics measurements

450 GeV detailed 

2

2

In progress

A6

450 GeV - two beams

OK 

1

1

OK

A7

Collisions at 450 GeV

OK 

1

1

To do in 2010

A8

Snapback and ramp

OK 

2

4

Without problems to 3.5 TeV.

A9

Flat top checks

OK 

2

1

In progress

A12

Commission experimental magnets

OK 

 

 

  Complete.

A10

Setup for collisions - 3.5 TeV

OK 

1

1

  Completed 29th March

 

Physics un-squeezed

 

1

-

  First collisions 30th March

TOTAL to first collisions

 

 

22

A11

Commission squeeze

OK 

2

6

  First trial performed (to 5 m in IR1&5)

A5

Increase intensity

 

2

6

  Work still in progress!

 

Set-up physics - partially squeezed.

  OK

1

2

  Operation scenario for 2010=, beta*=3.5 m

 

Pilot physics

  OK

 

 

 

 

 

Comments to: Mike Lamont