NB Beam Dumping system covered by Verena here

    Comments SW HW
Timing

Check application functionality - tables, events, telegrams, monitoring, energy

  • Test circulate and dump - looping in sequencer
  • Friday: JJG table - first pass

need to prepare timing tables

  • Inject Beam 1 (triggers BI capture events)
  • Inject Beam 2 (triggers BI capture events)-
  • Inject Beam x and start dump beam x table after 10 s
Delphine Julian, Stephane, Ioan
Injection Kickers
  • On Wednesday - pulse both 2 & 8 to nominal voltage, control from application
  • OASIS
  • Logging of waveforms
  • start with auto-generated pre-pulse by Etienne
  • Friday - expect pre-pulses from RF - need to check ring1/ring2 logic very carefully
  GHH Etienne
Injection requests
  • First tests of functionality - to "CBCM"
  • Alternate ring1/ring2
  Delphine Stephane
Power converters Converters in 2-3 to VS_SIM. Test all usual functionality from equip state Generate actual and ramp and squeeze (7 TeV nominal)   Steve
RF   Waiting on pre-pulses on Friday   Andy

Collimators
c/o Stefano

settings- discrete for "open", "coarse", "protect"
settings - ramp
settings - squeeze
Drive - collimators in 3,2,8,6 as available - tbc Stefano
Drive - lab collimator with squeeze function
BLMs - individual monitors
BG - can Atlas dummy up something?
Temperature
Logging
Fixed Display
Sequencer: drive actual injection settings(HARDWARE defined), check until armed, send timing event (dummy task for the time being), check until idle.
At the end of injection plateau, move out injection protection devices only: check that idle, drive actual settings for injection protection devices OUT, send timing event (dummy task for the time being), check until idle.
  Stefano Stefano
BLM
  • Check that last BLMs in transfer lines added to application and logging
  • LHC BLM study buffer working...no application yet though to check
    Lars/JJG
DIP
  • Check distribution of timing stuff
  • Check distribution of handshakes
  • Check disribution of beam related stuff
  Mike  
BCT
  • Check acquistion, logging and fixed display
  • Slow BCT looks good.
  • Fast BCT crates not responding
  • Dump BCT crates not responding (expected).
    Lars/JJG
BPM
  • Change sensitivity (Equip state).
  • set capture bunch and turns
  • Concentrating threading and capture -
  • Check concentration and write to SDDS.
  • Display from SDDS browser and multiturn application. OK
  • Check that last BPMs in transfer lines added to YASP and logging
  • Have concentrator working for BeamThreading and GetCapData
    Lars/JJG
YASP
  • orthoganal steering, threading etc. Interface to LSA settings etc. sound.
  Jorg  
SCREENS
  • In/out,
  • video
  • sdds
  • fixed display
  • BTVs in injection region; However, cannot move BTVST in point 2, TDI is not baked out
  • BTVs in video channels and fixed displays
  • BTV SDDS logging in TI 2 logging
    Lars/JJG
BLMs
  • acquisition
  • concentration
  • logging
  • sdds
  • display
    Lars/JJG
FIXED DISPLAYS
  • injection kickers
  • power converters
  • screens
  • BCT
  • Page 1 (mode)
  • etc. etc.
     
LSA
  • Actual settings drive trim with payload and timing event
  • Trim actual physics parameter
  • Trim actual strength.
  • Trim actual current.
  • (plus usual ramp settings - now thoroughly tested)
     
RBAC
  • Vertical Slice to power converters
  • Equip state RBAC enabled and tested
  • other stuff this time?
     
TI8 TED
  • ?
     
FIDEL
  • [Import 23 coefficients and generate transfer functions and harmonics and apply]
  • Auto Trimming of b3 (test example) during decay on injection plateau successfully test [possible]
     
SYNC LIGHT
  • Application test
     
WIRE SCANNERS
  • Application test
     
LOGGING
Full logging of all of above in place.      
SEQUENCER Come's in strong on Friday      

LSA Run Control

(from sequencer)

  • set fill number and push to timing and DIP
  • set mode and push to timing and DIP
  • set bunch configuration push to timing and DIP
  • set handshakes and push to DIP