450 GeV - preliminary commissioning

Pretty much the same as full commissioning

Aim: Get the machine in a good enough shape that we can sensibly start performing detailed adjustment and measurements and checks. No point in details if we're not sure the basic optics is not correct and the beam instrumentation isn't working properly. And safely increase the number of bunches plus intensity.

Prerequisites: reasonable lifetime, circulating pilot, roughly adjusted tunes, chromaticity, orbit and coupling

Exit:

Additional aims

  1. Test the control and correction  (corrector polarity, cabling, control system, software, procedures, …).
  2. Commission beam loss monitors - acquisition, display etc. no connection to BIC for the moment  - PARASITIC
  3. Commission beam dump - phase 1 - ESSENTIAL
  4. Commission beam interlock system with beam - phase 1. BIC to dump with beam. Check.  - ESSENTIAL
  5. Commission transverse diagnostics - PARASITIC
  6. Measurement program with pilots: what can we usefully do with this intensity? Polarities, aperture (first pass) - DO
  7. Linear optics checks: check trajectory versus kick, phase advance, BPM and corrector polarity. - DO
  8. Adjust tunes, orbit, chromaticity, coupling.  ESSENTIAL
  9. Commission BCTs: lifetime measurement PARASITIC
 
Team
Sub-phase
Total Time
both rings
Priority
450 GeV
Collisions
RF
Beam control loops (Phase, Synchro, Radial). Tuner loop, RF Feedback loop. Synchronisation
24
1
Essential
OP/AP
Test control and correction (corrector polarities, cabling, control system, software, procedures …).  Measure & correct orbit.
16
1
Essential
OP/BI
Commission transverse diagnostics - tune measurement [FFT].  Measure and adjust tunes, chromaticity, and coupling.
16
1
Essential
OP/AP
Linear optics checks: check orbit versus kick, phase advance, BPM and corrector polarity.
24
1
MD
BI
Commission beam loss monitors - acquisition, display etc. No connection to BIC for the moment.
12
1
Parasitic
BT
Commission beam dump - phase 1
24
1
Essential
BI
Commission BCTs: lifetime measurement
-
1
Parasitic
MPS
Commission beam interlock system with beam - phase 1. BIC to dump with beam. Test.
8
1
Essential
   
5 days
 
3 days

1. Initial Tuning of 450 GeV Machine

2. Systematic Pickup and Corrector Polarity Check and Aperture Scan

4. Revisit the Injection Settings

5. Initial Commissioning of the Beam Dump.

& re-visit

6. Other Measurements/ Corrections