Pretty much the same as full commissioning
Aim: Get the machine in a good enough shape that we can sensibly start performing detailed adjustment and measurements and checks. No point in details if we're not sure the basic optics is not correct and the beam instrumentation isn't working properly. And safely increase the number of bunches plus intensity.
Prerequisites: reasonable lifetime, circulating pilot, roughly adjusted tunes, chromaticity, orbit and coupling
Exit:
Additional aims
|
Team
|
Sub-phase
|
Total Time
both rings |
Priority
|
450 GeV
Collisions
|
|
RF
|
Beam control loops (Phase, Synchro, Radial). Tuner loop, RF
Feedback loop. Synchronisation
|
24
|
1
|
Essential
|
|
OP/AP
|
Test control and correction (corrector polarities, cabling,
control system, software, procedures …). Measure & correct orbit.
|
16
|
1
|
Essential
|
|
OP/BI
|
Commission transverse diagnostics - tune measurement [FFT].
Measure and adjust tunes, chromaticity, and coupling.
|
16
|
1
|
Essential
|
|
OP/AP
|
Linear optics checks: check orbit versus kick, phase advance, BPM
and corrector polarity.
|
24
|
1
|
MD
|
|
BI
|
Commission beam loss monitors - acquisition, display etc. No
connection to BIC for the moment.
|
12
|
1
|
Parasitic
|
|
BT
|
Commission beam dump - phase 1
|
24
|
1
|
Essential
|
|
BI
|
Commission BCTs: lifetime measurement
|
-
|
1
|
Parasitic
|
|
MPS
|
Commission beam interlock system with beam - phase 1. BIC to dump
with beam. Test.
|
8
|
1
|
Essential
|
|
5 days
|
3 days
|
1. Initial Tuning of 450 GeV Machine
2. Systematic Pickup and Corrector Polarity Check and Aperture Scan
4. Revisit the Injection Settings
5. Initial Commissioning of the Beam Dump.
& re-visit
6. Other Measurements/ Corrections