External Links

 

 

LHC Commissioning with Beam

Following consoldidation, cool-down and testing of the whole machine at cold, the latest schedule sees the re-start of beam commissioning in November 2009. This will be followed by a physics run through the winter until autumn 2010 starting at an initial beam energy of 3.5 TeV.

3.5 TeV will not be possible before Christmas. Given around 3 weeks of commissioning with beam before the end of the year, we hope to provide collisions at 450 GeV and perform initial commissioning of the ramp to 1.1 TeV.

Stages

    • Stage A: Initial commissioning with a single bunch moving towards 43 bunches on 43 bunches (moving to 156 on 156) with moderate intensities. First collisions un-squeezed; followed by partial squeeze.

    • Stage B: Move to 50 ns. bunch spacing with the aim of moving to intensities around 3 - 4 1010 particles per bunch

    • Stage C : Move to 25 ns. with the aim of moving to intensities around 3 - 4 1010 particles per bunch. Would need to be followed by long shutdown for  installation of phase 2 collimation and additional beam dump dilutors.

    • Stage D: Nominal 25 ns running pushing towards design intensity and full squeeze.

Stage A - phases & progress from 2008 - to be continued in 2009

Phase
Schedule/Progress
Notes
Ring
factor
Total Time [days]
both rings
Comments
A1
2
4
Time includes injection tests
A2
2
2
Beam one still to do
A3
2
4
In progress for beam 2
A4
2
4
Priority 1 measurements only
A6
 
1
1
Low intensity
A7
 
1
1
 Performance    Bring CMS (and other experiments') solenoids on before - measure and correct coupling
A8
 
2
4
Single and then two beams. Testing, systems preparation will be required before first serious ramps (~ 2 days)
A9
 
2
1
Single beam initially, performed following successful ramp
A12
 
     
A10
 
1
1
 
 
Physics un-squeezed
 
1
-
 
TOTAL to first collisions
 
 
22


A11
 
2
6
 
A5
 
2
6
 
 
Set-up physics - partially squeezed.
 
1
2
 
 
 
Potential performance in 2009

Evolution of stages

Stage Estimated time Comment
Stage A: establish first collisions
2 months
1 month beam time, 50% machine availability
Stage A: pilot physics
1 month
crossing angle off, max 156 bunches,
might expect 1031 cm-2s-1 and around 3 pb-1

156x156 at 1e32 will be a very important achievement, but just a milestone on the road toward 1e33 luminosity. No many-month long physics run with 156x156 will be planned, unless unexpected limitations are found during commissioning.
Stage B: 75 ns - commissioning
2 weeks
Interleaved with physics
Stage B: 75 ns - physics
1 month
Gradual increase in intensity, squeeze
5 x 10^32 cm-2s-1
Stage C: 25 ns physics
Intensity limited, 10^33 cm-2s-1 would be good


The 450 GeV Calibration Run planned for November 2007 which aimed to establish first beam collisions at a centre of mass energy of 0.9 TeV has been put on ice. However, collisions at 450 GeV are planned as we go for 5 TeV in 2009 and the requisite commissioning described above is still valid.

 
  Comments to: Mike Lamont